Contractual chain
It is common practice on construction projects to have more than one set of parallel contractual arrangements in place. On the one hand there is the main contract between the employer (client) and the main contractor; on the other hand, there is the sub-contract between the main contractor and the sub-contractor or sub-contractors. Each of these contractual arrangements is regarded as a link in the overall contractual chain.
One of the features of the contractual chain is the privity of contract. This means that the rights and obligations contained in the contract apply only to those who are a party to it. So, the main contract between the client and main contractor does not involve the sub-contractor who is therefore not liable contractually to the client for any actual breach of contract. The subcontractor therefore cannot claim against the client for say, poor working conditions or for retention monies held by the main contractor which have yet to be received. The sub-contractor must claim against the main contractor.
Likewise, the sub-contract between the main contractor and the sub-contractor does not involve the client. If the client wishes to claim against the sub-contractor, whether for the latter committing breach of contract or for defective work, the claim must be redressed by the main contractor. In such cases, the sub-contractor is liable to the main contractor.
There is usually no privity of contract between the client and the sub-contractor (whether nominated or domestic). So, for whatever breach of contract, fault or misdemeanour, the sub-contractor is not usually liable to the client. Which means the client cannot claim against the sub-contractor but must recover any due costs from the main contractor (with whom they have privity of contract). The main contractor in turn recovers the costs from the sub-contractor. This amounts to a chain of liability, where recovering costs requires either going up or down the contractual chain.
Problems can arise where the chain involves a weak link. For example, if the terms of the main contract and the sub-contract are not comparable, are incompatible or are just different, relying on the chain of liability could be problematic. There may be a break in the chain which would see the sub-contractor unable to recover any payments or compensation which are rightly due.
On large or complex projects, responsibility and performance generally cascades down the supply chain to a plethora of suppliers, some of whom may be entirely unknown to management at the top of the chain.
For more information see: Supplier and Supply chain.
NB Collateral warranties are agreements which are associated with another 'primary' contract. They provide for a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract. A typical example would be where an architect of a development owes a duty of care to an occupier of the development in so far as any subsequent defects which may arise are concerned. Privity of contract rules would prevent any liability arising between the architect and occupier without the existence of a collateral warranty.
For more information see: Collateral warranty.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.